Purpose of the SCANROC KEFSVOK-1 installation system

Installation of the hinged ventilated facade SCANROC KEFSVOK-1 is carried out on fencing structures made of dense building materials, since the system SCANROC KEFSVOK-1 does not provide for the installation of a heater, then the fencing structure should already meet the requirements of building norms for the conductivity
Fastening of the SCANROC KEFSVOK-1 system is made directly to the wall surface
Usually used for lining house structures and structures constructed of porous 440-510 mm thick ceramic blocks and other materials, if the resistance of the wall thermal conductivity Rпр ≥ [Rтр]
Device of structural metal part of the SCANROC KEFSVOK-1 system

All metal parts of the system are made of high quality European hot-dip galvanized steel.
All screws and anchors have hot-dip galvanized coating.
Explanation of the scheme:
- The wall
- Dowel
- Hot dip galvanized screw
- SCANROC C-1 or C-1.75 stand
- The facade tile SCANROC
The SCANROC C-1 rack is directly mounted on the SCANROC tile.
The diagram shows the placement of SCANROC C-1 racks in 600 mm increments for LONG Format [600x 100 mm] and LARGE Format [600x 200 mm] tiles. To hang the tiles of the COTTAGE Format cottage format [300×100 mm], the number of SCANROC C-1 racks is doubled in 300 mm increments.
Accessories SCANROC KEFSVOK-1 systems




Stages of installation of the SCANROC KEFSVOK-1 system
Perform markup according to the project. Drill holes to install anchor bolts.
Insert the dowel into the prepared holes.
The depth of the hole should be slightly larger than the length of the dowel.
Install the rack and secure it with hot-dip galvanized dowel screws.
Screw diameter 4,5… 4, 8 mm.After mounting the consoles, be sure to check the tightening of the nuts.
After mounting the entire system, the SCANROC tiles are mounted on the protruding antennae of the SCANROC C-1 racks.Hanging is done by pressing on the tile and planting its groove on the mustache of the rack C-1.
Each tile should have 3 points of resistance – left, right edges and middle. At a minimum, every fifth row should be fixed with additional anti-vandal antennae, which have SCANROC C-1 racks, unless otherwise provided by the project.